June 26, 2012

Thompson Stairs

(Photo by Kirby Varacalli)

Construction on the front steps at Thompson Middle School began on Tuesday morning, as crews worked to demolish the set of concrete stairs.

The bid to complete the project was awarded to W.H. Peppes of Lincoln and will cost $84,475. The group most recently completed work on the King Park retaining wall project.

The project at Thompson includes: Demolition of existing stair sections (3) and semi-circular landing and installation of (3) new concrete stair sections and landing. Stair treads at all three landings will be rough-cut granite.

June 26, 2012

Comments (1)

Comment Feed

Wasted $$$

This is an example of waste, anyone would know not to put cement stairs in a high traffic area or this is what happens. Also the landing area was sinking, where is the original bond covering poor work gone, was not the contractor bonded ? We should be responsible for the stairs and he should pay for the landing area. This was evident 2 years ago.

Jack 333 days ago